Here are the complete details of Ravi Riverfront Urban Development Project
Availability of Water:
Total rain days on the catchment of Ravi in Pakistan : 30-40
Average annual rainfall :650mm
Source of flows in river: (rain fall runoff+ Marla Ravi link Canal + Seepage water from Indian side)
Water in the river on 5-08-2020 : 25000 Cfs (17000 MR link canal water +3000 seepage water from India + rainwater)
Creation of Lake:
River will be channelized stating from 5 kilometres down stream of BRB canal up to Hadira drain width of one kilometre
Capacity of lake: 271 billion liters
Ground water extraction for domestic+ industrial use 4 billion litters/day
Seepage + evaporation from lake: one billion litters / day
Addition of 2.4 billion liters/day in to river Ravi in low flow seasons
Waste Water Treatment Plants
Treatment of 2.4 billion litters/day
Total cost Around 100 billions
This additional water will irrigate 75000 acre of land
Surface water Treatment Plant
Provision of 2.4 billion litters /day safe drinking water from canal water
Key Highlights of the project:
URBAN DESIGN
The RRFUD project is divided into three phases. Their areas are given below:
Area of phase – 1 = 44,817 acres
Area of phase – 2 = 25,668 acres
Area of sub-phase – 2 = 8,218 acres
Area of phase – 3 = 23,568 acres
Area(Acres | City | Developable Land | Phase |
5559 | Medical City | 3385 | 1 |
4093 | Residential City | 2456 | 1 |
4286 | Government and Finance City | 2495 | 2 |
1370 | Innovation City2 | 871 | 2 |
5169 | Knowledge City | 3024 | 3 |
5300 | Mix Use | 3227 | 1 |
30346 | Sports city | 14410 | 3 |
2924 | Tourism and Entertainment | 1796 | 2 |
5748 | Eco City | 3449 | 3 |
2208 | Downtown | 1325 | 1 |
723 | Commercial | 434 | 1 |
2352 | Urban Farms | 1411 | 1 |